Construction Act 1996

The deadline that costs most is the one nobody counted

Miss a pay-less notice and the sum applied for becomes the sum due. Not the sum you valued. The sum they asked for. QScope counts the days so that never turns on someone being on holiday.

30 days free · No card required · Every feature on every plan

Four dates, from one due date

The Housing Grants, Construction and Regeneration Act 1996 sets the payment timetable, and the contract form sets the day counts within it. Get the form wrong and every date after it is wrong.

Enter the due date once. QScope returns the whole sequence and recalculates it if the due date moves.

  • JCT SBC and DB, JCT IC and MW, NEC3 and NEC4, and the Scheme
  • Weekends and UK bank holidays excluded automatically
  • Bespoke payment period supported where the contract sets its own
  • Dates printed on the certificate, not just shown on screen
Payment
Statutory dates, JCT SBC/DB
Due date15 Aug 2026
Last date for payment notice due + 520 Aug 2026
Last date for a pay-less notice final - 524 Aug 2026
Final date for payment due + 1429 Aug 2026
Scheme applies instead17 and 7 days
NEC3 or NEC414 and 7 days

Miss the pay-less notice and the application is the debt

The sanction in the Act is not a fine. It is that the sum the contractor applied for becomes the sum due, in full, whatever it was actually worth. A pay-less notice one day late is a pay-less notice that does not exist.

QScope counts the pay-less deadline back from the final date for payment and warns while there is still time to issue one, because after that deadline the figure is fixed by law, not by your valuation.

  • Pay-less deadline counted back from the final date for payment
  • Warning raised while a notice can still be issued
  • The sum applied for shown against the sum you valued
  • Overdue deadlines separated from those still open
Payment
Pay-less position, PC-04
Sum applied for£16,400.00
Sum you valued£14,031.00
Last date for a pay-less notice24 Aug 2026
Days remaining4
If no pay-less notice is issued by 24 Aug 2026, the sum due becomes £16,400.00, the amount applied for, and not the £14,031.00 you valued.

Every live project on one screen

A single job is easy to keep in your head. Nine jobs across three surveyors is where notices go missing, and it is never the project you were thinking about.

The project list carries a deadline panel that sorts by urgency, so the job in trouble reaches you rather than waiting to be found.

  • Sorted by what is closest, not by project name
  • Overdue shown separately from approaching
  • Counts the days as of today, every time you open it
  • Straight through to the certificate that needs issuing
All projects
Payment deadlines
ProjectDateStatus
11 Essex Road, pay-less24 Aug4 days
Mill Lane, payment notice21 AugOverdue
Corn Exchange, final date2 Sep13 days
Bridge Works, pay-less9 Sep20 days

The dates belong on the certificate that carries them

A payment notice under section 110A has to state the sum due and the basis for it. The statutory dates are only useful if they print on that same document, next to the figure they govern.

QScope puts the due date, the final date for payment and the pay-less deadline on the face of the certificate, so the client is not counting days from a separate email.

  • Statutory statement printed on the certificate
  • Due date, final date for payment and pay-less deadline on the face
  • Your practice name and logo, never QScope branding
  • The valuation is the stated basis for the sum considered due
Client Valuations
Interim certificate PC-04
Gross this period£24,180.00
Less retention at 5%(£1,209.00)
Net due this certificate£14,031.00
The sum considered due at the payment due date of 15 Aug 2026 is £14,031.00. The basis on which it is calculated is the valuation above.

The other date that costs money

The pay-less deadline is the date that costs money this month. The retention release is the date that costs money after everyone has moved on, and unclaimed retention is the most commonly forgotten money in the industry.

QScope counts the release from the practical completion date and the rectification period, and warns on the project list as it approaches, the same way it warns on payment deadlines.

  • Half the retention released at practical completion
  • Balance released at the end of the rectification period
  • Release date warned on the project list, sorted by urgency
  • Held figure matches the retention notice sent to the client
Retention
Position at PC-04
Rate now
5.0%
Held
£4,205
Release
7 Sep 27
Practical completion7 Sep 2026
Rate before PC5.0%
Rate after PC2.5%
Rectification period12 months
Questions

What surveyors ask before they start

Which contract forms are supported?

JCT SBC and Design and Build, JCT Intermediate and Minor Works, NEC3 and NEC4 ECC, and the Scheme for Construction Contracts. Each carries its own day counts for the final date for payment and the pay-less notice.

Does it handle bank holidays?

Yes. The calculation excludes weekends and UK bank holidays, which is where hand counting usually goes wrong, particularly around Easter and the August bank holiday.

What if our contract sets a different payment period?

Enter it in the project settings and QScope uses your figure instead of the default for the contract form. The pay-less deadline is then counted back from your final date for payment.

Is this legal advice?

No. QScope calculates dates from the figures and contract form you enter. It does not check that the form you selected is the one that actually applies, and the notices you issue remain your professional responsibility.

Related

The rest of the commercial picture

Try it on your next valuation

Not your whole portfolio. One live job, one certificate. If it does not save you time the first time you use it, walk away and take your data with you.