Reports

The reports you actually send

Not a report builder with forty options. Four documents a QS produces every month, each already laid out the way a client expects to receive it.

30 days free · No card required · Every feature on every plan

Cost report: tell them early

A cost report exists so the client hears about an overrun while something can still be done about it. Delivered at final account it is not a report, it is an invoice they never agreed to.

Anticipated final cost sits against the approved budget from the first valuation onwards, with the contingency drawn from your risk register rather than guessed.

  • Anticipated final cost against approved budget, variance stated as a figure
  • Committed but not yet certified shown separately from certified
  • Contingency carried from the risk register, so it can be defended
  • Variance printed in words and numbers, never signalled only by colour
Reports
Cost report to client
Approved budget
£230,000
Anticipated
£224,800
Variance
+£5,200
Certified to date£84,115.00
Committed, not certified£18,400.00
Risk allowance carried£5,200.00
Anticipated final cost£224,800.00

Retention notice and payment schedule

Two documents that exist to stop an argument before it starts. The retention notice tells the client exactly what is held and when it comes back. The payment schedule shows every certificate, what was due and what was received.

  • Retention held, released at practical completion, and the balance date
  • Every certificate with net due, received and outstanding
  • Variation register listing each change, its basis and its status
  • All four on your letterhead, printed in black and white
Reports
Payment schedule
CertificateDueReceived
PC-01, 15 May 2026£3,482£3,482
PC-02, 15 Jun 2026£428£428
PC-03, 15 Jul 2026£9,140Outstanding
Outstanding to date£9,140.00

Printed to survive a bundle

Reports get photocopied, scanned and attached to adjudication papers. Anything that relies on colour stops being readable at that point, and a report that cannot be read is a report that cannot be relied on.

Every document QScope prints is black and white, with negative amounts in brackets and figures set in tabular numerals so columns line up.

  • Your practice name and logo, never QScope branding
  • Client purchase order printed so their accounts team can match it
  • Totals closed with a double rule, the accounting convention
  • Readable after photocopying, which is the only test that matters
Reports
What prints
Cost report, anticipated final costClient
Retention noticeClient
Payment scheduleClient
Variation registerClient
Risk registerInternal

The cash forecast a funder actually asks for

A cost report tells the client where the final number is heading. A cash flow tells a funder when the money moves. They are different questions, and QScope prints both.

The forecast is built from the certificates already issued and the valuation schedule ahead, so the peak funding requirement is a document you can hand over rather than a figure defended from memory.

  • Peak funding and the month it occurs stated as figures
  • Receipts from certificates against payments to subcontractors
  • Cumulative position printed month by month
  • Says plainly what it does not include
Cash flow
Forecast for the funder
Peak funding
£186,400
Occurs
Nov 26
Cycles left
5
Sep 26 · actual(£142,900)
Oct 26 · actual(£171,300)
Nov 26 · forecast(£186,400)
Dec 26 · forecast(£164,100)

The report you keep, behind the one you send

The cost report faces the client and never mentions margin. Behind it sits the cost and value reconciliation, the internal report that says whether the job is actually making money.

Both work from one cut-off date, so the anticipated final cost you show the client and the margin you keep to yourself are two views of the same period, not two different projects.

  • Value earned against cost incurred to one cut-off date
  • Margin and margin percentage, period by period
  • Kept internal, hidden from client guest links
  • Prints for internal reporting on your letterhead
Cost and value
Period to 30 Nov 26
Value
£93,300
Cost
£86,100
Margin
7.7%
Certified value£84,115
Done, not certified£6,400
Variations at settlement value£2,785
Value to the cut-off£93,300

Every report is the live position, printed

The reports are not a separate set of numbers you keep in step by hand. Each one is a printed view of the dashboard, taken at the moment you print it.

Contract sum, certified to date, retention held and due this period stay current as you value, so the cost report you send and the figure you quote on the phone are the same figure.

  • Figures recalculated as you value, across every project
  • Contract sum, certified, retention and due this period first
  • The closest statutory deadline shown underneath
  • No separate report data to keep in step
Dashboard
Ref 001, 11 Essex Road
Contract sum
£220,250
Certified to date
£84,115
Retention held
£4,205
Due this period
£14,031
Payment positionDateStatus
Last date for payment notice20 AugIssued
Last date for a pay-less notice24 Aug4 days
Final date for payment29 AugDue
Questions

What surveyors ask before they start

Can I change what the reports look like?

The layout is fixed, and deliberately so. These are documents that go into client files and adjudication bundles, and a consistent format is worth more than a configurable one. What changes is your logo, your practice name and your client reference.

Why is everything printed in black and white?

Because certificates and reports get photocopied and scanned. A figure that is only red stops being a warning once it is grey. Negative amounts appear in brackets instead, which is the accounting convention and survives any amount of copying.

Does the client see the risk register?

Not unless you print it for them deliberately. It is hidden from guest links by default, because a client who can read your contingency will always want to negotiate it.

Can I export the figures rather than print them?

Yes. The audit trail exports to CSV, and project data can be exported at any time, including during a trial and for 60 days after a cancellation.

Related

The rest of the commercial picture

Try it on your next valuation

Not your whole portfolio. One live job, one certificate. If it does not save you time the first time you use it, walk away and take your data with you.