NEC3 and NEC4 ECC

NEC pays on its own calendar

NEC does not use JCT valuation dates, JCT certificates or JCT retention. It uses assessment dates, a Project Manager and Option X16. QScope follows the NEC mechanism instead of bending it into a JCT shape, because the differences are where the money and the deadlines move.

30 days free · No card required · Every feature on every plan

The assessment date sets the whole cycle

Under NEC the amount due is assessed at each assessment date, not at a JCT interim valuation date. Every statutory deadline that follows is measured from it, so the assessment date is the pivot the rest of the timetable turns on.

Under Option Y(UK)2, the option that makes an NEC contract comply with the Construction Act, the payment becomes due seven days after the assessment date, and the final date for payment follows from there. QScope derives the notice, the pay less deadline and the final date from the assessment date automatically.

  • Assessment dates set from the starting date and the assessment interval
  • Payment becomes due seven days after the assessment date under Y(UK)2
  • Final date for payment fourteen days after that, or your Contract Data period
  • Pay less deadline calculated back from the final date, not guessed
NEC payment dates
Assessment 04
Assessment
24 Aug
Due
31 Aug
Final date
14 Sep
Assessment date24 Aug 2026
Payment becomes due (+7)31 Aug 2026
Pay less notice by11 Sep 2026
Final date for payment (+14)14 Sep 2026

The Project Manager certifies, and it is not a JCT certificate

Under NEC the Project Manager certifies the payment. There is no contract administrator issuing an interim certificate, and calling the document by its JCT name misdescribes who did what and under which clause.

QScope names the document for the contract it belongs to. On an NEC job it is a payment certificate issued by the Project Manager, on your letterhead, with the sum and the basis of its assessment stated.

  • Payment certificate named for NEC, not a JCT interim certificate
  • The Project Manager shown as the person who assesses and certifies
  • Sum due and the basis of the assessment stated on the document
  • Issued on your practice letterhead, ready to send
NEC payment certificate
Issued by the Project Manager
Price for Work Done to Date£231,400.00
Less retention under X16(£6,942.00)
Less amounts already certified(£209,300.00)
Sum due this assessment£15,158.00
Assessed by the Project Manager at the assessment date of 24 August 2026. Payment becomes due on 31 August 2026.

Retention exists only if Option X16 is in the contract

NEC has no retention unless secondary Option X16 was included. Deducting it when X16 is absent holds money you have no right to. Forgetting it when X16 is present overpays. Neither is a rounding error.

Where X16 applies, QScope holds retention on the Price for Work Done to Date above the retention free amount, at the percentage your Contract Data states, and releases it on the NEC triggers rather than the JCT ones.

  • Retention applied only when you turn it on, never assumed
  • Retention free amount respected, so early assessments can carry none
  • Half released in the assessment after Completion of the whole works
  • The balance released after the Defects Certificate is issued
Retention (X16)
Position at assessment 04
Rate
3%
Free amount
£0
Held
£6,942
Retention on work to date£6,942.00
Released at Completionnot yet
Held to Defects Certificate£6,942.00

The same valuation engine, pointed at NEC

The way QScope values the works does not change between forms. Percentage or fixed sum per line, previously certified carried forward, retention taken once. What changes on an NEC job is the label on the dates and the certificate, not the arithmetic underneath.

That means a practice running both JCT and NEC jobs works one way, not two, and the certificate a client receives reads the same whichever form the job sits on.

  • One valuation method across JCT and NEC
  • Line by line against the priced works, by percentage or fixed sum
  • Previous assessments carried forward automatically
  • The commercial position of every job on one dashboard, regardless of form
Client Valuations
Assessment 04, valued line by line
DescriptionThisAmount
Substructure100 %£0.00
Frame and upper floors55 %£18,200.00
CE-06 additional drainage100 %£3,900.00
Price for Work Done to Date, movement£22,100.00

Every statutory deadline in one place

The value of NEC date handling is not one certificate, it is the whole job seen at once. Which assessment is due, which payment is approaching its final date, which pay less window is about to close.

QScope puts the same statutory engine behind every NEC job on the account, so the dates you cannot afford to miss sit on the project list rather than in a spreadsheet somebody has to remember to open.

  • Due date and final date for payment on every assessment
  • Pay less deadline shown before it closes, not after
  • Assessment cycle set once and rolled forward
  • The same dates on the certificate the client receives
Statutory payment dates
Across the account
JobFinal dateStatus
Riverside, assessment 0414 SepDue
Bridge Street, assessment 079 SepPay less window open
Next final date for payment9 Sep 2026
Questions

What surveyors ask before they start

Which NEC forms does QScope support?

NEC3 and NEC4 ECC, as a contract form for the payment cycle. Selecting it sets the assessment date as the basis for the timetable, names the certificate as a Project Manager payment certificate, and applies the NEC retention rules under Option X16.

Does QScope assess compensation events?

It records each compensation event and its agreed value and carries that into the certificate, the same way it handles a variation. It does not replace the Project Manager's assessment of Defined Cost. The judgement stays with the Project Manager; QScope holds the record, the value and the certificate.

How does QScope handle Y(UK)2?

Under Y(UK)2 the payment becomes due seven days after the assessment date and the final date for payment fourteen days after that. QScope uses those periods by default and lets you change them if your Contract Data states different figures.

Is there retention on an NEC job?

Only if secondary Option X16 is in the contract. QScope applies retention when you turn it on, at the percentage and retention free amount your Contract Data states, and releases it at Completion and the Defects Certificate rather than at practical completion.

Related

The rest of the commercial picture

Try it on your next valuation

Not your whole portfolio. One live job, one certificate. If it does not save you time the first time you use it, walk away and take your data with you.