Ascertained means calculated from evidence, not estimated. A single figure with no basis behind it invites an ascertainment of nil, and that is a defensible outcome.
5 min read · All help topics
Loss and expense needs a relevant matter under clause 4.21. An extension of time needs a relevant event under clause 2.29.
Prolongation calculated as the tendered weekly preliminaries multiplied by the weeks of delay is a price, not a loss. The claim is for what was actually incurred, evidenced from the accounts.
Claimed and ascertained are shown separately, because they are different numbers and conflating them damages the credibility of the rest of the account.