The award is a number of weeks. What makes it defensible two years later is the sentence explaining how you got there, and that sentence is the thing nobody writes down.
5 min read · All help topics
A relevant event under clause 2.29 can carry an extension of time. A relevant matter under clause 4.21 can carry loss and expense. The lists overlap heavily and they are not the same.
The revised completion date moves. Liquidated damages then run from the new date, not the old one.
Any certificate of non-completion issued against the old date is cancelled and has to be reissued. QScope flags the damages calculation until it is.