New Zealand

An extension of time is a notice, then a proof

An extension of time moves the finish line and keeps liquidated damages off the contractor. Under NZS 3910:2023 it turns on a notice given in time and a delay evidenced against the programme, not on how busy the job felt.

QScope Team · 20 May 2026 · 6 min read

An extension of time adjusts the date for completion when something outside the contractor control delays the works. It is not extra money on its own, it is protection. Without it the original date stands, and liquidated damages start running against a contractor who was delayed by something that was not its fault.

Notice comes first

Under NZS 3910:2023 the extension mechanism runs through the Engineer to the Contract, and it starts with notice. The contractor has to notify the delay event and its likely effect on the programme within the contractual timeframe. A late notice weakens the claim, and a claim that only surfaces at the final account rarely survives.

  • The event. What happened, when, and why it falls under the contract as grounds for an extension.
  • The effect. How the event delayed completion, shown against the accepted programme.
  • The records. Site diaries, correspondence and progress data that fix the event in time.
An extension of time is won on the programme and the records. The feeling that the job was late is not evidence.

Cause tied to effect

The Engineer assesses the extension by looking at whether the event actually delayed completion, not just whether it happened. That means the claim has to link the event to the critical path. A delay to work that had float behind it may not move the completion date at all. The programme is where that argument is won or lost.

Time and money are separate

An extension of time protects the programme. It does not automatically bring cost with it. Where the delay also caused the contractor to incur additional cost, that is a separate claim on its own grounds, valued and, where it belongs on the works, carried into a payment claim. Keeping the two questions apart keeps both cleaner.

Why it matters for the account

The extension sets the completion date, and the completion date drives practical completion, the start of the defects period and the release of retention. Get the extension wrong and every downstream date drifts with it. Where the Engineer assessment is disputed, adjudication under the Construction Contracts Act 2002 is open to the contractor.

The discipline

Notify early, keep the programme current, and build the cause and effect while the event is fresh. The extension you can prove is the extension that holds, and the damages you avoid are worth more than the notice ever cost to write.

QScope does this part for you

QScope logs the delay events, ties them to the programme, and packages the extension claim the Engineer to the Contract needs to assess it.

Start free trial

Keep reading

Related

Try it on your next valuation

Not your whole portfolio. One live job, one certificate. If it does not save you time the first time you use it, walk away and take your data with you.